Tuesday, April 28, 2009

Appliances

The stove is in place and the power has been connected. The gas person will stop by and make the final connection for the stove and run the gas line test.
The dishwasher is in place, still need electrical hookup and a plumbing adjustments.
The fridge has been moved from the living room and is now in the kitchen and will be up and running tomorrow. The counter outlets, under cabinet lighting, ceiling can linghting and island lighting will also be installed tomorrow. Then we can take all the blue plastic wrap off the dishwasher and fridge.

I asked my daughter CJ what she wanted for her first real home cooked meal and she voted for Chicken Devine instead of Pizza for friday movie night. I guess even teenagers can get tired of pizza after 10 plus weeks. Complete project photos and before and after slide show will follow later this week.




Wednesday, April 22, 2009

Backsplash


The installation is complete except for the grout work. The stove hood has been installed and the propane tank and line have been installed, they couldn't hook up the stove because the power outlet in not installed. Tomorrow the backsplash will be grouted and the dishwasher and sink plumbing will be installed.


Friday, April 17, 2009

Backsplash tile is finally in.

Next week should be the last week. The backsplash tile is in. I have light fixtures for the island and over the sink. The gas man should be able to install the line mid next week.





I have painted most of the dining room. I took the kitchen/hallway color and painted it above the chair rail. I painted the chair rail and window trim the same trim color as the kitchen trim. Then I painted below the chair rail a darker color. I also painted the ceiling so that the hallway transition looks much better. I will have to paint the wall between the kitchen and dining room after the contractor fixes a crack in the wall. Yes, I know I need a new light fixture.






Tuesday, April 7, 2009

Counters are In






The counters are in, and look great. Now the only major thing is to wait for the backsplash tiles to be in.

Counters, Finally!!

The last two weeks have been slow, we have been waiting for the counter/installers to be available. But some progress has been made. The light rails have been installed.
All the trim work and ceiling has been painted. The first coat of paint is on the small area of wall in the kitchen not covered by cabinets and tile. The backsplash tile should be in on friday, if all goes well the backsplash will be installed next monday.


The hallway area has been painted the same color as the kitchen and the hallway closet has been painted ceiling white (its only been 20+ years since the closet hase ever been painted). I am planning to run the kitchen color into the dining room, either above the chair rail or below the chair rail, then I will paint the other area a lighter color. I also plan to paint the window trim and chair rail the same color as the kitchen trim.



Today the counters are going to be installed. It should make a big difference in the look of the kitchen. The propane service person came yesterday, and will get back to me with the cost of the new service install. I think we will go with the additonal grill switch box to make summer grilling a little easier, no more opps the grill tank is empty.

Sunday, March 22, 2009

Cabinet Hardware


I ordered hardware for the cabinet doors special ordered from Lowes. I need 53 pulls! I dont think I realized just how many cabinets we will have in the new kitchen. I was hopping that lowes had some longer ones that matched there every-day ones (6 inch ones were only 4.00) but even they looked the similar, the depth was different.

The are similar to the one in the photo. The ones for the bottom the tall cabinets are 13 inches and the rest are 5 3/4 inches.

Friday, March 20, 2009

The Crown


The molding is in place. WOW! I cant believe how nice it looks. What a different look with the molding. Thanks to SG's work on squaring up the room and KG for the hard work in making things look great.
I think we have a winner for the backsplash tile. I am not sure what type of stone it is, but its from the Mordern Mythology line by crossville inc. Its a 2x4 inch stone tile (the one next to the counter sample). Not sure if we will add any details (kind of like the dark rounded bullnose strip, it also comes in a 2x4 in that same color) but still thinking about it. This photo is not that great, the counter material is not rally that dark.

The counter people are comming next week to template the counter, island and desk area.
I also picked out a realy cool looking sink faucet.
Now we need to work on the paint.